CS605 Assignment No - 03 - Fall2011


CS605                          Assignment No. 03 - Fall2011

Question:
Let us assume that you are working as a Team lead in a renowned multinational company. The software project has 80 planned work tasks that are estimated to require 415 person-days to complete. At the time you have been asked to compute the Earned Value Analysis, 8 tasks have been completed. However, the project schedule indicates that 18 tasks should have been completed. The following scheduling data in person-days are available:
Compute the following:
1)      SPI
2)      Schedule variance
3)      Percent scheduled for completion
4)      Percent complete
5)      CPI
6)      Cost variance for the project.