Let us assume that you are working as a Team
lead in a renowned multinational company. The software project has 80 planned
work tasks that are estimated to require 415 person-days to complete. At the time you have
been asked to compute the Earned Value Analysis, 8 tasks have been completed.
However, the project schedule indicates that 18 tasks should have been
completed. The following scheduling data in person-days are available:
Compute the following:
1)
SPI
2)
Schedule variance
3)
Percent scheduled
for completion
4)
Percent complete
5)
CPI
6)
Cost variance for
the project.